Following the anticipated major rehabilitation, and upgrading of Epifanio de los Santos Avenue (EDSA), the Department of Public Works and Highways – National Capital Region is actively preparing to implement the rehabilitation works by segments, one lane at a time, starting from the EDSA bus lane.

By end of March 2025, the one segment of the rehabilitation will start in the northbound portion from Quezon City/Caloocan boundary to Monumento. The DPWH-NCR assures that the EDSA bus carousel will remain operational, however, it will be temporarily relocated on its adjacent lane, while EDSA bus stations remain open for the commuters. Once the closed segments from the first lane are fully rehabilitated, the EDSA bus lane will move back to its original lane to accommodate its regular operations.

Regular updates and developments on the rehabilitation activities, including traffic management plan for EDSA will be posted on the official social media channels of the DPWH-NCR. 